All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Inspect, fault find, remove, install/replace and adjust a steady arm and/or side strain insulator on overhead traction equipment (OHTE) under "live" and/or isolated and earthed conditions |
SAQA US ID | UNIT STANDARD TITLE | |||
119887 | Inspect, fault find, remove, install/replace and adjust a steady arm and/or side strain insulator on overhead traction equipment (OHTE) under "live" and/or isolated and earthed conditions | |||
ORIGINATOR | ||||
SGB Electrical Engineering & Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Civil Engineering Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 4 | NQF Level 04 | 11 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
The learner credited with this unit standard will be able to independently:
A steady arm and/or side strain insulator on OHTE safely and correctly under "live" and/or isolated and earthed conditions thus contributing to the safe running of electric trains, as well as ensuring the continuity of power supply in the Rail Sector. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
It is assumed that learners are competent in:
|
UNIT STANDARD RANGE |
Equipment may include but is not limited to:
Statutory requirements may include but are not limited to: Work procedures may include but are not limited to company's: Manufacturers' specifications may include but are not limited to: This unit standard includes the installation of a steady arm and/or side strain insulator under "live" 3-kV DC and/or isolated and earthed conditions. Work permit conditions apply when work is performed under isolated and earthed conditions. |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Communicate with relevant role players and complete relevant documentation. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Job card is interpreted correctly, and specified work executed correctly. |
ASSESSMENT CRITERION 2 |
Relevant documentation is completed correctly. |
ASSESSMENT CRITERION 3 |
Communication related to the inspection, fault finding, removal, installation/replacement and adjustment of a steady arm and/or side strain insulator on OHTE is carried out effectively. (Operating and Electrical control). |
SPECIFIC OUTCOME 2 |
Prepare to inspect, fault find, remove install/replace and adjust a steady arm and/or side strain isolator under "live" and/or isolated and earthed conditions. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Tools, equipment and material are obtained and verified for correctness. |
ASSESSMENT CRITERION 2 |
Safe loading and off-loading of tools, material and equipment are ensured for correctness. |
ASSESSMENT CRITERION 3 |
The necessary safety precautions at the worksite are taken to prevent injury to personnel. |
ASSESSMENT CRITERION 4 |
Work permit is obtained correctly and timeously when work is performed under isolated and earthed conditions according to work-permit procedures. |
ASSESSMENT CRITERION 5 |
Protection is placed correctly according to TWR. |
ASSESSMENT CRITERION 6 |
Transport is arranged for personnel. |
SPECIFIC OUTCOME 3 |
Inspect, fault find, remove, install/replace and adjust steady arm and/or side strain insulator under "live" and/or isolated and earthed conditions according to company specific instructions and manufacturer's specifications. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Company-specific safe work procedures are followed correctly. |
ASSESSMENT CRITERION 2 |
Tools and equipment are placed and used safely and correctly. |
ASSESSMENT CRITERION 3 |
Steady arm and/or side strain insulator with accessories are/is assembled correctly. |
ASSESSMENT CRITERION 4 |
Lifting equipment is used safely and correctly in accordance with statutory requirements. |
ASSESSMENT CRITERION 5 |
Steady arm and/or side strain insulator are/is inspected for defects in accordance with steady arm and/or side strain insulator inspection procedures. |
ASSESSMENT CRITERION 6 |
Steady arm and/or side strain insulator are/is removed, replaced/installed correctly in accordance with steady arm and/or side strain insulator removal, replacement/installation procedures. |
ASSESSMENT CRITERION 7 |
Steady arm and/or side strain insulator are/is adjusted correctly in accordance with steady arm adjustment procedures. |
SPECIFIC OUTCOME 4 |
Finalise the inspection, faultfinding, removal, installation/replacement and adjustment of steady arm and/or side strain insulator under "live" and/or isolated and earthed conditions. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Quality checks are performed safely and correctly on steady arm and/or side strain insulator as per company-specific instructions and manufacturer's specifications. |
ASSESSMENT CRITERION 2 |
Tools, equipment and material are removed safely and correctly. |
ASSESSMENT CRITERION 3 |
Worksite is cleared according to company-specific instructions. |
ASSESSMENT CRITERION 4 |
Protection is removed correctly in accordance with TWR. |
ASSESSMENT CRITERION 5 |
Work permit is cancelled correctly and timeously according to work-permit procedures when permit was issued. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
Moderation options:
|
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Learners can understand and explain:
|
UNIT STANDARD DEVELOPMENTAL OUTCOME |
Learner and societal development:
Learners can understand the importance of: |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Problem solving:
Learners can solve problems with regard to: |
UNIT STANDARD CCFO WORKING |
Teamwork:
Learners can work effectively in teams when: |
UNIT STANDARD CCFO ORGANISING |
Self-organisation and self-management:
A learner can organise and manage oneself by: |
UNIT STANDARD CCFO COLLECTING |
Information evaluation:
Learners can interpret and evaluate the contents of: |
UNIT STANDARD CCFO COMMUNICATING |
Learners can communicate effectively with relevant role-players when:
|
UNIT STANDARD CCFO SCIENCE |
Use of science and technology:
Learners can use science and technology, by using: |
UNIT STANDARD CCFO DEMONSTRATING |
Inter-relatedness of systems:
|
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
Values:
Supplementary information: Terminology: Job order refers to: Communication media can include but are not limited to: |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 49774 | Further Education and Training Certificate: Construction and Maintenance of Overhead Track Equipment | Level 4 | NQF Level 04 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | TETA |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | Palesa Rail Academy |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |