All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Install or replace electrical metering units or measuring instrument |
SAQA US ID | UNIT STANDARD TITLE | |||
10233 | Install or replace electrical metering units or measuring instrument | |||
ORIGINATOR | ||||
SGB Electrical Engineering & Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Electrical Infrastructure Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 2 | NQF Level 02 | 4 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2007-04-03 | 2009-02-18 | SAQA 0160/05 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2010-02-18 | 2013-02-18 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard is replaced by: |
US ID | Unit Standard Title | Pre-2009 NQF Level | NQF Level | Credits | Replacement Status |
258919 | Install or replace electrical metering units or measuring instrument | Level 2 | NQF Level 02 | 4 |
PURPOSE OF THE UNIT STANDARD |
This unit standard is for persons in the Electrical Engineering; Generation; Distribution; Transmission, Construction and Renewable Energy Sector A person credited with this unit standard will be capable of:
This unit standard will contribute to the full development of the learner within the electrical engineering and construction environment by providing recognition, further mobility and transportability within the field of Physical Planning and Construction. The skills, knowledge and understanding demonstrated within this unit standard are essential for social and economic transformation and upliftment within the electrical engineering and construction environment. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
The following knowledge, skills attitude and / or equivalent:
|
UNIT STANDARD RANGE |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Plan to Install and/or replace an electrical metering units or measuring instruments. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Task requirements are interpreted according to instructions and/or diagrams. |
ASSESSMENT CRITERION 2 |
2. Metering units or measuring instruments are selected and obtained as per specifications. |
ASSESSMENT CRITERION 3 |
3. Tools and equipment are selected according to job requirement. |
ASSESSMENT CRITERION 4 |
4. Location for mounting is correctly identified. |
ASSESSMENT CRITERION 5 |
5. Authorisation is obtained for access to restricted areas and possible downtime. |
ASSESSMENT CRITERION 6 |
6. Safety equipment and material required are obtained. |
ASSESSMENT CRITERION 7 |
7. Working schedule is communicated to affected parties. |
SPECIFIC OUTCOME 2 |
Install a metering unit or measuring instrument. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Area is correctly prepared for the mounting procedure. |
ASSESSMENT CRITERION 2 |
2. Metering unit or measuring instrument dimensions are marked off as per specifications. |
ASSESSMENT CRITERION 3 |
3. Hand and power tools are correctly selected and used to meet the requirements of the job. |
ASSESSMENT CRITERION 4 |
4. Metering unit or measuring instrument is mounted and secured. |
ASSESSMENT CRITERION 5 |
5. Metering unit or measuring instrument is connected as per instruction / specification. |
ASSESSMENT CRITERION 6 |
6. Safety precautions are adhered to before, during and after the mounting procedure. |
SPECIFIC OUTCOME 3 |
Replace a metering unit or measuring instrument. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Job instructions are interpreted and a sequence of operation is planned. |
ASSESSMENT CRITERION 2 |
2. Job tasks are carried out in accordance to the sequence of events. |
ASSESSMENT CRITERION 3 |
3. Faulty meter is identified and the replacement meter selected correctly. |
ASSESSMENT CRITERION 4 |
4. Ensure circuit is isolated according to statutory requirements and worksite procedures. |
ASSESSMENT CRITERION 5 |
5. Safety precautions are taken during the removing and replacing process. |
ASSESSMENT CRITERION 6 |
6. Connections are correctly matched. |
ASSESSMENT CRITERION 7 |
7. Metering unit or measuring instrument is replaced and secured according to specifications. |
SPECIFIC OUTCOME 4 |
Complete the Installing and/or replacing of a metering unit or measuring instrument on a panel. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. The re-energizing of the circuit is ensured and correct operation of replaced metering unit or measuring instrument is verified. |
ASSESSMENT CRITERION 2 |
2. All waste materials or scrap materials and equipment are discarded as per environmental / safety policies and standards. |
ASSESSMENT CRITERION 3 |
3. All tools and equipment is checked, cleaned and stored correctly as per work site standards and procedures. |
ASSESSMENT CRITERION 4 |
4. Workplace restored to original state as per housekeeping standards and work site procedures and standards. |
ASSESSMENT CRITERION 5 |
5. All relevant administration such as Job card, is signed off and submitted. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
1. Anyone assessing a learner against this unit standard must be registered as an assessor with the relevant ETQA.
2. Any institution offering learning that will enable achievement of this unit standard must be accredited as a provider through the relevant ETQA by SAQA. 3. Moderation of assessment will be overseen by the relevant ETQA according to the moderation guidelines in the relevant qualification and the agreed ETQA procedures. |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Knowledge that will help me understand and that I will be able to explain:
|
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO WORKING |
Tasks using responsible thinking and decision making (in relation to the use and choice of relevant personal protecting equipment and safety equipment). |
UNIT STANDARD CCFO ORGANISING |
Organise oneself and one`s activities responsibly and effectively (in the ability to follow instructions when working by ones self or in a work team, ensure safe execution of work activities). |
UNIT STANDARD CCFO COLLECTING |
Collect, evaluate, organise and critically evaluate information related to (installing and or replacing an electrical metering unit or measuring instrument; correct identification of colour coding). |
UNIT STANDARD CCFO COMMUNICATING |
Effective use of communication methods when (giving instructions to fellow workers, following of instructions, recording and reporting information). |
UNIT STANDARD CCFO SCIENCE |
Use science and technology effectively and critically, showing responsibility towards the environmental and the health of others (installing and or replacing an electrical metering unit or measuring instrument) to ensuring that all safety and environmental conditions are considered). |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
UNIT STANDARD NOTES |
This unit standard has been replaced by unit standard 258919, which is "Install or replace electrical metering units or measuring instrument", Level 2, 4 credits.
This Unit Standard was originally registered on 12 June 2002 under SAQA decision number 0742/02. It has been re-registered on 11 February 2004 under SAQA 2552/04. Credits: Total hours required by the learner to achieve the required outcomes: Total of 40 hours. |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 20418 | National Certificate: Electrical Engineering | Level 2 | NQF Level 02 | Passed the End Date - Status was "Registered" |
2004-02-10 | Was EWSETA until Last Date for Achievement |
Core | 48473 | National Certificate: Electrical Engineering | Level 2 | NQF Level 02 | Passed the End Date - Status was "Reregistered" |
2009-02-18 | Was EWSETA until Last Date for Achievement |
Elective | 58269 | National Certificate: Electro-Mechanics | Level 2 | NQF Level 02 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | As per Learning Programmes recorded against this Qual |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
NONE |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |